1. INSTALLATION OF THE STRUCTURE AND THE TEMPLATE:
For this crucial step, we call upon a surveyor to first establish the level of the meter which will be our reference for the entire construction project.
Then we proceed as follows:
- Surveyor's visit to mark the excavation holes
- Surveyor's visit to mark the footings
- Surveyor's visit to mark the posts
The advantages of this method compared to the traditional method
are the precision of the execution which will later be visible on the masonry and
also the speed of execution.
2. POURING THE SCREED AND SLABS
We use new formwork, whether it be planks
or panello.
– We use spruce trees for formwork support
for better security.
– We spray form release oil on our formwork timber to achieve better
concrete quality during formwork removal and also that
allows for much faster formwork removal.
3. MASONRY AND PLASTERING
Thanks to the scaffolding, the masonry is
executed in a quick and above
very precise without leaving any traces on the
facades which will later be seen during the
painting (because with the traditional method)
the planks are used as supports
for the workers and hang directly
on the facades).
For a perfect, flawless corner finish, we use
an aluminum template as a reference, so that our bay
a corner window can be fixed later onto a plaster
perfectly perpendicular.
4. ELECTRICIAN AND PLUMBER
These two trades, along with the company, are the key to the success of a construction project, both in terms of its progress and its proper execution.
Through our experience we have established a good network of subcontractors and thus we provide the best of these two trades on the Tunisian market.
ELECTRICIAN:
The boxes are installed right from the start, as soon as we finish the masonry work. This will prevent any later adjustments. We will then apply the plaster, following the level of these boxes, which were pre-established together during their installation. This saves time and ensures greater precision.
PLUMBER:
– The plumber works on supports with
earthenware, whether for the collectors or for the room
technique
– A layer of SP4 is pre-applied in the
bathrooms and duct stumps.
– We recommend the use of PVC
3 mm for better sound insulation and
better durability
– After the PVC pipes and conduits have been installed
the passage of grooved tubes (with thermal insulation)
everything is permanently placed in the boiler room
under pressure and we can pour our screed everywhere
even in the boiler room.
– We will call the plumber later
when we finish our coating
5. FINISHING
The finishing process begins with pouring the screed which
It must be precise so that everything follows correctly.
will use a laser for leveling the bandalisse
meter
Next, in this crucial step, we call upon
to qualified installers with whom we have already
collaborated. In this stage, monitoring is a very important task.
important.
Cutting equipment, disc replacement
as well as the use of drill bits of different diameters for cutting embedded bodies are very
important.
6. SWIMMING POOL
A permanent formwork is built after the excavations for the pouring of the concrete.
The tanking will be done by a qualified roofer who will
will take care of sealing the parts himself (skimmer, spotlights, return inlet).
will take care of sealing the parts himself (skimmer, spotlights, return inlet).
SIKA as well as the walls of the swimming pool.
We personally oversee the tanking process and guarantee it.
An initial filling without testing. Hence a great gain
on the quantity of water.